From due dates to a plan: using the timeline and milestones

Most boards start with due dates only. That is enough to know what is late, and not enough to know whether the project will finish on time. A due date says when something should end. A plan also says when it has to start, and which dates cannot move.

This post takes the Website Relaunch project from the Northwind Studio demo workspace (a fictional studio and a fictional client) and turns its due dates into a plan with the Timeline view. Nothing new is created: the timeline is a third view of the tasks already on the board.

What the timeline draws

Open a project and choose Timeline next to Board and List. Each task with dates becomes a bar; the rules are short.

On the taskOn the timeline
A start date and a due dateA bar from one to the other, labelled with the assignee
The milestone flagA diamond on the task’s date
Due date in the past, task not doneThe bar is red
Task completedThe bar is green
No datesThe task is listed as unscheduled instead of being hidden

A vertical line marks today, and the scale switches between weeks and months. Tasks stay grouped by their board column, so you can still tell what is in progress from what has not started.

app.delivergoals.com · Website Relaunch · Timeline
Timeline view of the Website Relaunch project from 1 November to 26 December 2026 on a weeks scale: bars from start date to due date labelled with the assignee, grouped by column; a vertical line on today, 15 November; Homepage hero and illustrations in red as overdue; diamond milestones for Beta open to customers on 22 November and Public launch on 6 December; a legend for Open, Done, Overdue and Milestone.
Website Relaunch from 1 November to 26 December. The line is today, 15 November. One bar is red. The two diamonds are the beta and the public launch.

Step 1: mark the dates that cannot move

Start from the end. Harbor & Finch, the client, has two fixed dates: the beta opens to their customers on 22 November and the site launches publicly on 6 December. Each is a task with the Milestone box ticked in the task panel. A milestone has no duration, so it is drawn as a diamond.

Keep milestones rare. If every task is a milestone, the diamonds stop meaning anything. Two for a six-week project is about right.

Step 2: give every task a start date

For each task, ask one question: given the due date, when does this have to start for that to be realistic? “Checkout flow redesign” is eight story points and is due on 15 November, so it started on 6 November. “Set up redirects from old URLs” is short: it starts the week it is due.

The start date is set in the task panel, just below the due date. Due dates can also be changed in the list view, which is quicker when you are adjusting fifteen tasks in a row.

app.delivergoals.com · Task DG-31
Task panel for Checkout flow redesign (DG-31): a description, three subtasks with 1 of 3 done (33%) and a Generate with AI button, a comment from Priya Nair with Reply, and on the right status In progress, section In review, priority Urgent, assignee Priya Nair, due date 11/15/2026 marked Due soon, start date 11/06/2026 with a Milestone checkbox, 8 points, 60% progress, labels Design and Engineering, a dependency Blocking: Beta open to customers, and an attachments drop area.
Start date and due date sit together in the task panel, with the Milestone box beside them.

Step 3: plan backwards from each diamond

With the diamonds and bars in place, read the chart from right to left. Everything the beta needs should end to the left of the first diamond; everything the launch needs should end to the left of the second.

Planning backwards from two milestones 6 Nov15 Nov (today)22 Nov6 Dec Checkout flow redesign Homepage hero Redirects Translate landing pages Beta open to customers Public launch Bars end before the diamond they serve. The red bar ended on 14 November and is not done.
The idea in one picture: bars that serve a milestone end before it. This is a simplified drawing of the demo project, not a screenshot.

In the demo this shows two things straight away. Translation work sits between the two milestones, which is right: the client asked for French and German pages for the launch, not the beta. And the three bars in progress all cross the today line, which means a lot is due in the same few days.

Step 4: look for red, then for crowding

The red bar is “Homepage hero and illustrations”. It was due on 14 November and is still in progress. On the board that is one red date among sixteen cards. On the timeline you can see what it sits next to: the checkout redesign ends a day later and the beta is a week away.

Crowding is the other thing to look for. If one person’s name is on four overlapping bars, the dates are a wish. The bars are labelled with the assignee for exactly this reason.

Step 5: deal with the unscheduled list

Tasks without dates are listed as unscheduled rather than being left off. In the demo, “Audit analytics events” in the backlog has no assignee and no date. That is a legitimate state for a backlog item, but check the list each week: a task that matters and has no date will not appear on anyone’s plan.

Weeks or months

Use Weeks while you are working inside the plan: each day is a column and a one-day slip is visible. Use Months when you show the plan to someone else, such as a client, who wants the shape and the two diamonds and not the daily detail.

What the timeline does not do

Dependencies are recorded on tasks (blocks and blocked by) but are not drawn as lines between bars. There are no sprints or burndown charts. The timeline is a picture of the dates on your tasks; keeping those dates honest is still your job.

A plan is the dates plus the habit

The whole method fits in four lines:

  1. Flag the fixed dates as milestones.
  2. Give every scheduled task a start date as well as a due date.
  3. Once a week, open the timeline: fix what is red, spread what is crowded, schedule or drop what is unscheduled.
  4. When a date changes, change it on the task and say why in a comment.